Construction Update



Last updated: September 2010

August 2010 works at the Northpoint project are nearing to completion of the project. Corridors are substantially complete and the remaining penthouses Tower A and upper units PRC Tower B near final trades works completion. Home owner inspections are continuing according to hand over programme.

Apartment fit-out works are nearing completion, with corridors, fire escape stairs and common areas now completed. All external cleaning of all facades, aluminium and glass and external louvers have been completed. Sky gardens at level 29 tower A and level 24 tower B are complete and gymnasiums have been equipped and tested. All management offices and back of house facilities are occupied and functional.

Final mechanical & electrical, fire protection and waste water system are operational.

Externally, swimming pools, slides and water feature works all operational and in full use. Canopies to the car drop-off zones are complete. The main entrance guard house and site boundary wall construction works are complete while final finishes to the road surfaces have now been completed.

Car park building roof-top the tennis court is complete. The car park building painting works have been completed together with planter box façade installations and irrigation systems. Additional improvements to weatherproof the car park lift lobbies together with some minor finishing improvements are nearing completion. Security controls and access systems are now fully operational.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: August 2010

July 2010 works at the Northpoint project are nearing to completion of the project. Corridors are substantially complete and the remaining penthouses Tower A and upper units PRC Tower B near final trades works completion. Home owner inspections are continuing according to hand over programme.

Apartment fit-out works are nearing completion, with corridors, fire escape stairs and common areas now completed. All external cleaning of all facades, aluminium and glass and external louvers have been completed. The lift car fit-out works continue, one additional lift per building have been completed and are undergoing final testing and commissioning and are due for final certification in August.

Final mechanical & electrical, fire protection and waste water system are operational.

Appointed property managers, Savills Thailand, are now fully mobilized and responsible for the ongoing management of the buildings and services.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: July 2010

June 2010 works at the Northpoint project have moved into the final phases of finishing works primarily on corridors and the remaining penthouses Tower A and upper units PRC Tower B. Phased home owner inspections are continuing according to hand over programme.

Apartment fit-out works are nearing completion, with corridors, fire escape stairs and common areas being brought toward final completion. Building signage has been completed throughout the project. At both towers the ongoing external final cleaning of all facades, aluminium and glass and external louvers are being completed by spider men. The lift car fit-out works continue, two lifts per building have already been completed. Lift Car testing and commissioning on the remaining lift cars is progressing and will be due for final certification in August. Sky gardens at level 29 tower A and level 24 tower B are now complete and gymnasiums have been equipped and tested. All management offices and back of house facilities are occupied and functional. MATV antennae are now installed and connected.

Final Mechanical & Electrical, Fire Protection and Waste Water system tests have been completed and have been formally handed over to the facility manager for ongoing operation.

Externally, all the softscape and landscape plantings have now truly taken root and being to flourish with the onset of early rains. Swimming pools, slides and water feature works all operational and in full use. Canopies to the car drop-off zones are installed and complete. The main entrance guard house and site boundary wall construction works are complete while final finishes to the road surfaces have now been completed.

Car park building roof-top the tennis court is complete and playable. The car park building painting works have been completed together with planter box façade installations and irrigation systems. Additional improvements to weatherproof the Car Park Lift lobbies have been commenced together with some minor finishing improvements. Security controls and access systems are now installed and are fully operational.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: June 2010

May 2010 works at the Northpoint project continued with the pace of construction activity being markedly increased as we approach the final weeks. Phased home owner inspections are ongoing and ownership transfers are being processed to take advantage of the extended transfer tax relief scheme. There has been little adverse impact on the project due to the political situation in Bangkok.

Apartment fit-out works are continuing towards completion commensurate with corridors, fire escape stairs and common areas. Building signage has been completed throughout the project. At both towers the external final cleaning of all facades, aluminium and glass and external louvers are being completed by spider men. The main entrance lobby fit-out works are now complete at both towers and have been furnished. The lift car fit-out works continue, two lifts per building have already been completed. Sky gardens at level 29 tower A and level 24 tower B are now complete and gymnasiums have been equipped and tested. All management offices and back of house facilities are occupied and functional. MATV antennae are now installed and connected.

Final Mechanical & Electrical, Fire Protection and Waste Water system tests have been completed and have been formally handed over to the facility manager for ongoing operation.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: May 2010

April 2010 construction works at the Northpoint project continued with the pace of construction activity being markedly increased as we approach the final weeks. Phased home owner inspections are ongoing and ownership transfers are being processed to take advantage of the extended transfer tax relief scheme.

Internally, apartment fit-out works are continuing towards completion commensurate with corridors, fire escape stairs and common areas. Building signage is being installed throughout the project. At both towers the external decorative paint finishes are now complete and external final cleaning of all facades, aluminium and glass and external louvers are being completed. The main entrance lobby fit-out works are now complete at both towers and are being furnished. The lift car fit-out works are now in process and two lifts per building have already been completed. Works to the sky gardens at level 29 tower A and level 24 tower B are now also practically complete. All management offices and back of house facilities are occupied and functional. MATV antennae are now installed and connected.

Externally, all the beachfront zone and area fronting tower B hardscape, softscape, swimming pools, slides and water feature works are complete. Tree planting and landscaping works to all remaining areas of the 12-rai site are likewise complete. Canopies to the car drop-off zones are installed and complete. The main entrance guard house and site boundary wall construction works are complete while final finishes to the roads are currently being installed.

At the car park building roof-top the tennis court is complete. The car park building painting works are virtually complete as are the wire mesh and planter box façade installations together with irrigation systems. Security controls and access systems are now installed and being commissioned.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: April 2010

Through March 2010 construction works at the Northpoint site continued towards completion. The final commissioning and testing of mechanical and central services and hand over to the Facilities Management has commenced. Raimon Land project team and CRM staff have been established within office facilities. Phased home owner inspections are continuing and ownership transfers are underway.

Internally apartment fit-out works are continuing up the buildings towards completion. The external flat and textured decorative paint applications are now complete. The lift car fit-out works are now in process at both towers.

Tree planting and landscaping works to all remaining areas of the 12-rai site are continuing. The main entrance guard house and site boundary wall construction works are in process. Final development of remaining water features is under completion and will be commissioned before Songkran. Main entrance drop-off canopies are being completed.

At the car park building roof-top, tennis court mesh boundary fencing installations are nearing completion. The car park building painting works are now complete as are the wire mesh and planter box façade installations. All temporary site offices of the various contractors are being relocated from car park building to an adjacent site. Access and security control systems are being installed at main entrance and car park.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: March 2010

Through February 2010 construction works at the Northpoint site continued towards completion. The building occupation permit has been secured and incoming mains water and electricity supplies are connected at the site. Phased home owner inspections have continued through February and ownership transfers are underway.

Internally apartment fit-out works are continuing up the buildings towards completion. At both towers the external flat and textured decorative paint applications are now practically complete and await final top coat only. The main entrance lobby fit-out works are now complete at both towers and have been furnished accordingly. The lift car fit-out works are now in process at both towers. Works to the sky gardens at level 29 tower A and level 24 tower B are now also practically complete.

Externally the beachfront zone hardscape, softscape, swimming pool and water feature works are complete with the swimming pools and lily pond water features having been water-filled and the jungle water slide installations are complete. Hardscape, softscape and water feature installations to the area fronting tower B are also progressing towards completion. Tree planting and landscaping works to all remaining areas of the 12-rai site are continuing. The main entrance guard house and site boundary wall construction works are in process.

At the car park building roof-top, tennis court mesh boundary fencing installations are progressing. The car park building painting works are now practically complete as are the wire mesh and planter box façade installations.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: February 2010

Through January 2010 construction works at the Northpoint site continued towards completion with phased incoming home owner inspections continuing in preparation for imminent unit ownership transfers to commence.

Internally apartment unit fit-out works are continuing up the buildings towards completion. At both towers the external flat and textured decorative paint applications are now practically complete and await final top coat only. The main entrance lobby fit-out works are now complete at both towers and have been furnished accordingly. The sky gardens at level 29 tower A and level 24 tower B are also practically complete.

Externally the beachfront zone hardscape, softscape, swimming pool and water feature works are complete with the swimming pools and lily pond water features having been water-filled. Hardscape, softscape and water feature installations to the area fronting tower B are also progressing towards completion.

More construction update photos are available on the Northpoint Facebook fan page.









 

Last updated: January 2010

Through December 2009 construction works at the Northpoint site continued towards completion and the first phase of incoming home owner inspections have commenced in preparation for unit ownership transfer.

Internally apartment unit fit-out works are continuing up the buildings. Externally the beachfront zone hardscape, softscape, swimming pool and water feature works are complete with the swimming pools and lily pond water features having been water-filled and the jungle water slide installations are complete.

At both towers the main entrance lobby works are now complete. The sky gardens at level 29 tower A and level 24 tower B are also practically complete. The fitness room areas are in the process of fit-out with all remaining gym equipment being delivered and installed at site.

The car park building painting, mesh and planter box façade installations remain ongoing towards completion.

More construction update photos are available on the Northpoint Facebook fan page.


Northpoint towers stand tall above Wong Amat beachfront


Lily pond fronting Tower A


Completed jungle water slide and kids pool area


The completed swimming pools and landscape area at the Wong Amat beachfront


50-metre lap pool at the beachfront now complete and water filled


The Tower A ground floor reception area


Sky garden level works nearing completion


The completed external works at the Wong Amat beachfront zone

 

Last updated: December 2009

Through November 2009 construction works at the Northpoint site continue apace with landscape, swimming pools and water features all progressing towards completion at the Wong Amat Beach front zone. The water slide has been constructed, swimming pools have been tiled and timber decking and other hardscape finishes are installed. The beach pavilion structure is complete and fit-out works internally are ongoing.

The main lobby area fit out works are progressing with stone feature walls and floors complete at tower A, all veneer wall paneling has been installed and finished, mezzanine levels installed and complete, and the bespoke reception counters installations are complete.

At the sky gardens feature timber ceiling installations are ongoing as are the swimming pool tile installations and other hardscape finishes. The sky garden fitness room areas are in the process of fit-out with all gym equipment being delivered and installed at site.

The car park building painting, mesh and planter box façade installations remain ongoing.

More construction update photos are available on the Northpoint Facebook fan page.













 

Last updated: November 2009

Northpoint continued to make good progress towards completion in the month of October.

The sky garden fitness areas are in the process of fit-out, with fitness equipment deliveries and installations ongoing throughout the past month.

Swimming pool waterproof testing works have been completed while tiling works have commenced. The fun water slide structure and retaining wall have been also been completed. Softscape package works have been procured and works are currently underway on site. Construction of the beach pavilion has also commenced throughout October. Overall, the external works are on schedule for completion by the end of December 2009.

At the car park, the structure is now in the process of receiving an external façade cladding system with planter boxes.


The completed structures stand tall above Wong-Amat beachfront.


Construction works in progress at the summit of Tower B.


Sky garden swimming pool installation works ongoing.


External swimming pool and water feature installations in progress at the beachfront.


Common area fit-out works in progress.


Hardscape works continue externally.


Car park façade in preparation to receive external cladding system installations.


External decorative paint applications continue towards completion at both towers.

 

Last updated: October 2009

Northpoint continues to make progress towards completion. Permanent power and water supply provisions have been connected to the site. The site underground drainage system installation works continue towards completion and the external hardscape, softsacape, and water feature installations made significant progress during the month of September.

Structural works are complete at both towers and the building is watertight. Externally the flat and textured decorative paint applications are nearing completion. Unit fit-out works are significantly advanced in both towers and the main entrance lobby areas are currently being fitted out, whilst works at lift lobby areas area significantly advanced.

At the car park, structural works are practically complete and roof surface preparation works are underway ready to receive the artificial grass tennis court installations.


Completed balcony on level 35 of the North Tower.


Living area of new show unit on level 35.


Kitchen and dining area in new show unit.


Master bedroom in new show unit.


Master bedroom and bathroom.


New show unit on level 35 of the North Tower.


Guest bedroom in new show unit.

 

Last updated: September 2009

The last month has seen continued good progress at the Northpoint site. The swimming pool reinforced concrete slabs have been cast and waterproofed, while the main access road water feature has been constructed and now awaits final finishes, as do lily ponds, walkways and the external hardscape, softscape, and water feature installations. At both towers the main entrance lobby fit-out works are progressing and are set to provide residents a fitting welcome to these world class residential buildings. Lift lobby area fit-out works also remain ongoing at both towers with limestone feature walling and floor tile installations ongoing.

Elsewhere, at the car park structural works are practically complete and will soon be ready for the tennis court installations at roof level. The external cladding system design is complete and is currently under procurement.


Access Road Water feature.


Completed Structure overlooking landscape works.


Landscape works ongoing.


Main lobby glazing installations ongoing.


Swimming pool and landscape works ongoing at Wong Amart beachfront.


Swimming pool Under Construction.


Tower B.

 

Last updated: August 2009

In the month of July, construction of Northpoint continued to make good progress. Underground drainage system installations are currently in process and the site clearance and piling works to the beachfront landscape area are complete, with pile casting for the main swimming pools complete and the reinforced concrete slabs being cast.

Elsewhere on site, the main entrance lobby areas are in the process of fit-out works with mezzanine floors and façade glazing being installed and the general lift lobby and corridor fit-out works progressing. At the car park, structural works are practically complete and will soon be ready for the tennis court installations at roof level.

Installation of the window and balcony sliding door system as well as the balcony glass balustrades is now substantially complete at both towers, whilst the electrical busduct installations are complete to the top levels with floor connections under progress and permanent power energized. The fit-out teams are working hard and continue to progress work up the buildings with imported floor and wall tiling; internal ceiling installations; kitchen fit-out and appliances; built-in wardrobes; vanity units, joinery doors and floors, and frameless shower cubicles installations well advanced.


Workers progressing landscape walkway at front of Tower B.


Workers preparing coridoor walls for final paint application.


Tower A & B structures complete.


Swimming pool works ongoing at beacfront with RC structure cast.


Landscape works in process between tower A and beachfront.


Glazing Workers preparing for main lobby glazing lift and Installation.


Decorative applications in process at rear of towers A and B.

 

Last updated: July 2009

Through June 2009 Northpoint continued to make good progress. Site clearance and piling works to the "Zone A" landscape area between the front of Tower A and the Wong-Amat Beachfront are ongoing. The pile casting for the main pools at the beachfront are now complete and reinforced concrete slabs are being cast.

Mechanical, electrical and plumbing first fix installations have progressed towards the penthouse levels of both towers, and the second fix installations are progressing significantly at both towers to follow. The electrical busduct installations are ongoing. Permanent power and water supply applications have been progressed and are expected to be connected at site according to programme. The passenger lift installations are ongoing with designated lifts having now been tested, commissioned, protected and handed over to the Main Contractor for temporary use during the remaining works. Two of four external temporary passenger hoists have been de-commissioned and removed from site accordingly. The transformer building reinforced concrete roof slab has been cast and associated waterproofing works completed.

Externally, the towers walls surface preparation and Lanko skim coat application process is ongoing and the textured and flat paint decorative applications to the façade are being progressed at both towers. Internal block work walls and plastering have been substantially completed, followed closely by installation of aluminium and glazing installations to the facade and balconies of the buildings. Imported Floor and Wall tiling installation works remain ongoing and have significantly advanced at both towers, internal Ceiling installations have progressed equally, followed closely by kitchen fit-out and appliances installations; built-in wardrobes installations; vanity units, joinery doors and floors, and frameless shower cubicles. Sanitaryware installations are also making good progress up the building at site with deliveries ongoing to the site commensurate with installation progress.

The main entrance lobby area to both towers are in the process of fit-out works with general lift lobby and corridor area fit-out works also progressing within the towers.


Surface preparation works and decorative paint applications ongoing.


Surface preparation works and decorative paint applications ongoing.


Textured paint works in process.


Landscape & swimming pool works ongoing at the beachfront.


Swimming pools structural works in process.


Piles have been cast and reinforced concrete slab works ongoing to beachfront swimming pools.


Lift lobby fit-out works progressing.


Unit H living room and balcony overlooking Wong Amat beachfront.

 

Last updated: June 2009

With Northpoint now a landmark on the Pattaya skyline, construction through May 2009 continues to make strong progress.

The demolition works on the beachfront sales offices and show unit building are complete and we have commenced the site clearance of the "Zone A" landscape area between the front of Tower A and the Wong-Amat Beachfront.

Setting out and piling works for the main swimming pools have now begun, with the external hardscape, softscape, and water feature installations to the 12-rai site expected to be complete within seven months subject to the wet season.

On the building exteriors, the external walls surface preparation and Lanko skim coat application process is ongoing and the textured and flat paint applications to the façade have now begun, which will see the building take on a new appearance over the coming months.

Inside the buildings, mechanical, electrical and plumbing "first-fix" installations have progressed towards the penthouse levels of both towers, and the "second-fix" installations are also progressing significantly in both towers. Installation of the passenger lifts is also ongoing, with lifts undergoing testing and commissioning for temporary use during the works.

Internal block-work walls and plastering are substantially complete, followed closely by the installations of aluminium and glazing to the facade and balconies of the buildings.

Imported floor and wall tiling works remain ongoing and have vastly advanced in both towers. Internal ceiling installations have progressed equally, followed closely by kitchen fit-out and appliance; built-in wardrobe; vanity units, joinery doors and floors, and frameless shower cubicles installations.


Tower A viewed from Wong Amart Beachfront.


Northpoint Tower A stands tall above the Wong Amat Beachfront.


Northpoint Towers standing tall over the Wong Amat coastline.


Piling Works ongoing to landscape Zone A Swimming pool area.


Landscape Piling Workers.


Completed Unit Tower B Level 35.


Kitchen Water Heater, Sink, washer dryer installations nearing completion.


Installation of light switches and Siemens thermostat.

 

Last updated: May 2009

Through April 2009 Northpoint continued to make progress despite the Songkran Holiday shutdown period. The demolition works at the beachfront sales offices and show unit building are now practically complete allowing for imminent commencement of the landscape package works to the 12-rai site. The new show units and sales offices have been re-located to level 3 of tower A and are facilitated by a new covered walkway that has been constructed between the sales office car park and Tower A.

Mechanical, Electrical and Plumbing first fix installations have progressed towards the penthouse levels, and the second fix installations are progressing significantly at both towers. The lift package works are due to be commissioned shortly for temporary services during the works and are significantly advanced in terms of overall progress.

The external walls surface preparation and Lanko skim coat application is ongoing and will soon be ready to receive textured and flat paint decorative applications. Internal block work walls and plastering have been substantially completed, followed closely by installation of aluminium and glazing installations to the facade and balconies of the buildings. Imported floor and wall tiling installation works remain ongoing and have significantly advanced at both towers, internal ceiling installations have passed level 25 in both towers, followed closely by kitchen fit-out and appliance installations; built-in wardrobe installations; vanity units, joinery doors and floors, and frameless shower cubicles. Sanitaryware installations are also making good progress with deliveries ongoing to the site.


Newly Constructed Walkway between Sales Car Park and Tower A


Newly Complete Show Unit at Tower A level 3


Electrician undertaking 2nd fix installations


Fit-Out Works progressing at Tower A


MEP Installations Ongoing at Coridoors


Unit receiving final decoration works


Tower B structure complete

 
 

Last updated: April 2009

At Northpoint, the beachfront sales office and show units are being demolished; a covered walkway has been constructed from the car park to the new sales facilities and show units at Level 3, Tower A. The landscape design is nearing completion and work will commence after Songkran.

The mechanical and electrical first fixing installations are progressing towards level 50 in both towers, while the second fix installations have significantly advanced. The lift installations are nearing completion in both towers, and will shortly be commissioned for temporary services.

Skim coat plaster to the external walls is under progress and will soon receive textured and flat paint decorative applications. Internal block work walls and plastering have been substantially completed, followed closely by installation of aluminium and glazing installation. Ceiling installations have passed level 20 in both towers, which are followed by kitchen fit-out; built-in wardrobes; vanity units and frameless shower cubicles.


The completed Structure Tower B viewed from the summit of Tower A


Spectacular view from the top of the structure


View from the back of the site showing completed structures and substantially complete car park building


Lift control panel, lift winding gear and motor installations ongoing


Jacuzzi bath tubs delivered to site for installation


Substantially complete corridor works at L3

   
 

Last updated: March 2009

The Northpoint construction site in Pattaya has been a hive of activity in February, and work remains on schedule. Now that both towers have been topped off and all structural work has been completed, the massive Tower Cranes have been removed, and the site has been receiving regular deliveries, with the electrical distribution board mains, transformers and fire pumps all arriving in February.

Interior and M&E (Mechanical and Electrical) works are making good progress. Block work walls, plastering and window frame installation have progressed to the high levels of both towers, whilst floor and wall tiling, ceiling installation, and kitchen fit-out works continue to progress up the building.


Aluminium & Glass Window System installations progressing


Bathroom fit out works ongoing at this unit


Completed Kitchen Fit-Out


Decoration Works ongoing at lower levels


Final works to a completed floor area


New covered walkway installations ongoing to new show units sales area at L3 tower A


The completed structures stand tall over wong amart beach

 
 

Last updated: February 2009

After the Northpoint "topping off" ceremony was completed on December 12, practical completion of the structural concrete works for Towers A & B is ahead of schedule. Fit-out works are ongoing in both towers and are proceeding to schedule while the car park building works are ongoing after the access road was relocated. Blockwork walls have been laid up to level 47 in Tower A and level 40 in Tower B, while aluminium and glass windows, balcony balustrades, and louvres have been installed as high as level 38 on Tower A and level 31 for Tower B.

Imported Italian stone floor and wall tiling has progressed to level 29 in Tower A and level 19 Tower B, while kitchen appliance deliveries are ongoing and installations have progressed to level 5 in both towers.


Above Ceiling pipe and ductwork installations


Balcony above ceiling CDU installations


Jacuzzi Bathtub Installation at Tower A


Kitchen Fit Out Works ongoing


Progress of the Glazing Installations at Tower A


The Completed Structures


The View at the top of Tower B

 
 

Last updated: December 2008

Construction at Northpoint is proceeding on schedule with over 1,000 workers on site daily progressing the works. Structural works on both towers is nearing completion and scheduled for "topping out" in mid-December 2008. Mechanical, electrical and plumbing installations are also making good progress, and have reached level 39 of both towers. Windows and balcony door frame installations are progressing at level 28 and the 3rd floor mock-up units in both towers are nearing completion. These mock up units will set the benchmark for quality levels to be achieved throughout the project.


Scaffolding being erected at the top of the tower


Looking across to the 2nd tower and the view of the bay


Lower floor level Interior fit-out now nearing final completion.


Looking up at the two towers


Spectacular views


Northpoint construction progress looking back from the beachfront.

   
 

Last updated: November 2008

Construction works are on schedule with slab casting due to take place at level 49 of Tower A and level 42 of Tower B shortly. Fit-out works are progressing well. Installation of the Italian floor tiles has progressed up to level 15 of Tower A and level 10 of Tower B. Bathroom shower as well as door, door frame and skirting installation is progressing on level 3 of both towers and the installation of cabinets and built-in kitchens has reached level 4. Meanwhile, a temporary road is under construction and will become the new access road for the sales offices and show suites.


Scaffolding in place, ready to lay rebar.


Tower crane positioning materials on Northpoint’s top levels


Northpoint site staff


Gondolas lifting materials to the upper levels


Rebar being laid and inspected in preparation for another pour


Structural rebar being laid

   
 

Last updated: October 2008


North Tower progress taken from atop South Tower

Glazing framework ready to be lifted in to position

View of the South Tower overlooking the bay

Structural framework ready to accept concrete


   

Skilled labour forming additional framework

Concrete and other materials being delivered to site

 

 

 

Last updated: September 2008


View of the main crane in action

Looking down from the construction hoist

View of the bay from Northpoint's construction hoist

Engineer inspecting frame-work


View of the bay from Northpoint's construction hoist

Erecting scaffolding, life lines in place

Looking up at the tower. Crane positioned atop the tower

Offloading materials.

 

Last updated: August 2008


Looking up at the tower

Cranes lifting materials into position

Site progress being surveyed

Structural concrete preparations


Materials constantly on the move

Materials constantly on the move

Concrete form-work

 

 

Last updated: July 2008


Scaffolding being erected.

Materials lifted to upper levels. Forming work.

Cranes lifting form-work into position.

View from above.


Site coordinators and foremen.

View from upper levels.

Forms ready to accept concrete.

Looking up from ground level.


View of 26th floor, tower B.

 

Last updated: June 2008


South Tower View from main entry to sales office

View of both towers. Tower cranes positioning materials for higher level installations

View of North Tower progress taken from South Tower

Interior image showing progress of M&E and glazing frame works


     

Lifting of materials and building supplies

 

 

 

 

Last updated: May 2008


Lift core structures from the building plant

North Tower reach Level 21-22

Preparing slabs for electrical installation

South Tower Duplex Units


   

South Tower reach Level 26-27

South tower with uninterrupted views to Pattaya

 

 

 

Last updated: March 2008


The View of the bay looking past Tower A (South Tower) Works

L-Shaped Balcony Structures becoming visible as work progresses on the side elevation of Tower A (South Tower)

Rear elevation view of Tower A (South Tower) Structural Works Progress

Birds-eye view of Tower B (North Tower) Structural Works Progress


View East over the rising Tower B (North Tower) Works Progress

Tower Crane Stands tall above the Car Park Building Works

Front façade view of Tower A (South Tower) progress taken from ground level looking over the existing Sales Office building

Side / rear building elevation view of Tower A (South Tower) Works progress

   

Rear Elevation of Tower A (South tower) showing structural works progress up to Level 14.

Front façade view of Tower B (North Tower) progress taken from ground level

   
 

Last updated: January 2008


Car park structure foundation

Construction site office

Form work system in action

Labour entry - exit point


North Tower

South Tower rises above the show suites

The South Tower rising above it all

The view from on top

     

Truck Cleaning Depot

     
 

Last updated: November 2007


South Tower (Tower A) Progress of Shear Wall Construction

South Tower (Tower A) Construction progress

North Tower (Tower B) Tower Crane TC2 for North Tower Works

Car Park Building - Progress of Foundation Works


     

Steel Rebar Yard. 6,000 tones will be delivered to site by end of November for entire project.

     
 

Last updated: October 2007


Assembling the tower crane

Foundations on North Tower

Foundations on the South Tower

 

Last updated: August 2007


Construction gates and progress signs onto Soi 16 Naklua

Boygues on site project offices

Silos stand over the on site batching plant

Overall site mobilisation


     

Project costruction headquarters on
the adjacent
Northpoint II site
 

     
 

Last updated: July 2007



     

Completion of piling at Northpoint

Last updated: May 2007



 

Last updated: March 2007


Pre-construction piling work lays a strong foundation for Northpoint